摘要: |
This paper is a brief case study of how a mega scale road project has been conceived and advanced to the stage of implementation within a fixed time scale of three years. A decentralized but coherent approach in planning, design and implementation made it possible to accomplish the tasks. A simultaneous approach to different individual components during the project preparation stage is the key to the success factors. This paper outlines the journey during project preparation stage with focus to the critical areas like availability of land, environment clearance and social acceptability. This 701 km long access controlled expressway with provision of user charges with a capital outlay of Rs. 55,000 Cr is being implemented on EPC mode. |