ONGOING: Work progressed on 18 of the 20 total bridges planned for reconstruction. Crews are currently widening 1-70 in the center segment between Colorado Boulevard and Quebec Street. Construction is progressing in the future lowered section of 1-70 between Brighton and Colorado boulevards, which is being built adjacent to the current 1-70 viaduct and will be drivable by late spring 2021. COMPLETED: Crews finished final paving and striping in the east segment between Quebec Street and Chambers Road, marking the completion of this segment. The new 46th Avenue North was also constructed between Colorado Boulevard and Steele Street, which will eventually serve as a frontage road along 1-70. Stapleton North Drive is now complete between Holly and Dahlia streets. |