Work is being carried out at a construction site in north Bavaria, next to the A93 Autobahn.The contract for the earthworks for the automotive supplier and technology park in Hof-Gattendorf was awarded to ARGE AMAND Bau Sachsen together with AMAND Bau. From the end of July to mid-November 2020, around 150,000m~3 of topsoil and around 680,000m~3 of soil was moved, paved and stabilised over a total area of 50ha. As good subgrade achieves optimum load bearing capacity for infrastructure and buildings, soil stabilisers have been deployed to improve much of the 680,000m~3 using binding agents.To achieve the required daily targets at the project, up to 580tonnes of binding agents need to be spread daily and milled into 13,000m~3 of soil. MEIER Bodenstabilisierung opted to use three large BOMAG unit from its fleet in order to meet the deadlines and required quality. |