摘要: |
Work is underway for the Beijing East Sixth Ring Road Reconstruction Project in China. The CRCHI mega slurry TBM Jinghua is working on the project and features a maximum excavation diameter of 16.07m, measures 150m in length and weighs in at 4,300tonnes. The machine is the largest shield TBM in China and benefits from systems such as fourth-generation accessible cutter exchange technology, telescopic main drive, high pressure auto-compensation, a large power slurry circulation system, and synchronous double-liquid grouting.The successful application of synchronous double-liquid grouting technology has delivered mm-level control of ground settlement, ensured zero disturbance to buildings on the surface and filled the gap of synchronous double-liquid grouting in mega slurry TBM construction in China. |