摘要: |
The airport operators needed to complete the runway reprofile without disrupting scheduled take-offs and landings. With an eye on speed, flexibility and quality, the operators opted to lay a series of new asphalt layers over the existing runway. Milling machines were used to rectify the profile of the runway, with asphalt pavers then being used to lay the asphalt layers each night. The runway then reopened each morning for normal airport operations to resume during the day. This was a complex project with no room for delays, but it went to plan. The plan was achieved due to the combination of a skilled team, 3D machine guidance, technology from Trimble and support and training provided by Trimble distributor, SITECH France. |