原文传递 Contractor Faces Legal Hurdle When Proving Its Delay Claim
题名: Contractor Faces Legal Hurdle When Proving Its Delay Claim
正文语种: eng
作者: Michael C. Loulakis;Lauren P. McLaughlin
作者单位: Capital Project Strategies LLC in Reston Virginia;Smith Currie & Hancock LLP in Tysons Virginia
摘要: There are times when a contractor believes its right to a time extension is so obvious that it does not need to support its claim with a typical scheduling analysis. This can occur when the contractor thinks that the owner is on the same page as to why the project was delayed. This months case, Appeal ofWright Brothers, The Building Company, Eagle LLC, provides an interesting lesson about this topic, explaining how a contractor that was delayed on a project by more than three years thought it had an understanding with the federal government that it was entitled to a time extension and additional money, only to lose the case entirely.
出版年: 2023
期刊名称: Civil Engineering
卷: 93
期: 4
页码: 20-21