当前位置: 首页> 国外交通期刊数据库 >详情
原文传递 Huntington District Updates Planned Lock Closure Schedule
题名: Huntington District Updates Planned Lock Closure Schedule
正文语种: eng
摘要: The Huntington Engineer District has revised its planned maintenance schedule through September 15 as part of a new Notice to Navigation Interests. On March 3, the primary chamber at Racine Locks and Dam, Ohio River Mile 238.0, reopened ahead of schedule following miter gate machinery repairs. Beginning March 6, filling system repairs began on the auxiliary lock chamber at Meldahl Locks and Dam, Ohio River Mile 436.2, requiring the chamber's closure. Repairs are anticipated to be complete about June 30. Beginning July 5, repairs will begin on the primary lock chamber at Gree-nup Locks and Dam, Ohio River Mile 341.0, requiring the chambers closure for dewatering and miter gate inspection and repairs. The auxiliary chamber will be available for lockage during this time. Repairs are anticipated to be complete about August 14. Marines may contact the lockmaster via marine channel 13 for more information.
出版年: 2023
期刊名称: The Waterways Jouranl
卷: 136
期: 47
页码: 11-11
检索历史
应用推荐