原文传递 L&D 25 Project On Schedule, Under Budget
题名: L&D 25 Project On Schedule, Under Budget
正文语种: eng
作者: DAVID MURRAY
摘要: The lock expansion project at Lock and Dam 25 poured its first concrete November 3 and had another pouring November 15. It is currently on schedule and slightly under budget. Whether that will continue to be the case depends on many things, according to Jose Lopez, program manager of the Lock and Dam 25 Expansion Project for the St. Louis Engineer District. The project will add a 1,200-foot lock chamber to the facility, built in the 1930s. Its current 600-foot chamber is a bottleneck, causing lock transits of three to four hours for large tows. The replacement lock will cut that transit time to 30 minutes. The project was authorized in 2007 but was not given any money by Congress until it was awarded $732 million in the Infrastructure Investment and Jobs Act in FY2022.
出版年: 2023
期刊名称: The Waterways Jouranl
卷: 137
期: 34
页码: 5,44