Construction of a new bridge over the Cumberland River at Smithland, Ky., remains significantly ahead of schedule, according to the Kentucky Transportation Cabinet (KYTC). The contractor resumed roadway work at the U.S. 60/Ky. 70 intersection on the south approach on May 19. KYTC District 1 Chief Engineer Kyle Poat said while there were some delays due to floodwaters during the fall and winter, the project appears to be approximately two months ahead of schedule. "The project is progressing at a great pace with the recent completion of the south main pier and placement of beams this week for span 3 on the south approach," Poat said. The contractor also poured concrete May 16 on the north main pier, the final pier remaining to be completed. |