摘要: |
Madam/Sir, In continuation to Ministry's Circular cited above, it is to state that keeping in view relaxation given by Government of India under "Atmanirbhar Bharat", the provisions of the said circular shall also be made applicable to schedule H of the ongoing projects being implemented on EPC mode of contract upto 31.03,2023. 2. It is further to state that to allow the similar facility in HAM Concession Agreement (CA), a sub-stage has been introduced in Annexure-I of Schedule G of HAM CA for calculation of progress against casting of precast items such as bridge girders and RE-wall facia panels/blocks for determining achievement of project milestones. 3. In view of above, the following amendments has been made in Annexure-I of Schedule G of HAM CA as shown in the last column of the respective tables in Annexure. The amendments shall be made applicable to ongoing HAM concession agreements upto 31.03.2023. 3. This is issues with the approval of Competent Authority. |