国家和地区: |
Mexico |
项目名称: |
General Felipe Angeles International Airport Project, Santa Lucia, Mexico |
领域: |
New Airport |
项目类型: |
ATC Tower,Airside Facilities,New Terminal,Runway,Taxiway |
项目性质: |
Public |
项目经费 (USD Millions): |
3899 |
规模: |
20 |
规模单位: |
million passengers per year |
参加单位: |
Government of Mexico[Sponsor]{Mexico},Secretaria de la Defensa Nacional (Sedena)[Sponsor]{Mexico} |
项目状态: |
Under construction |
开始时间: |
2019 |
结束时间: |
2022 |
项目说明: |
February 2022 - Project expected to be inaugurated on March 21 2022; April 2021 - Project is scheduled to open its doors in March next year; October 2019 - Construction commenced; Master plan for construction of the aerodrome was published in August 2018; Airport will feature two runways of 5.1 km and 4.6 km, a 4.7 sq km air base, control tower, terminal, taxiways, fuel terminal, cargo terminal and other associated infrastructure; Project cost - MXN75bn |
发布时间: |
2019 |