Grupo Villar Mir[Sponsor]{Spain},Philippines Department of Transportation (DOTr)[Sponsor]{Philippines}
项目状态:
At planning stage
开始时间:
-
结束时间:
-
项目说明:
October 2021 - Project under planning stage; February 2020 - Project proposal is already up for evaluation and approval of the National Economic and Development Authority (NEDA) after the Civil Aviation Authority of the Philippines granted original proponent status (OPS); May 2017 - Government scrapped bidding of the airport; February 2016 - Project will be built as part of 14 projects to be implemented through the Public Private Partnership (PPP); March 2015 - Funds allocated from DOTC for project; Project cost - PHP30.4bn