O'Hare International Airport Modernization - New 9C/27C Runway, Chicago, Illinois
国家和地区:
United States
项目名称:
O'Hare International Airport Modernization - New 9C/27C Runway, Chicago, Illinois
领域:
Airport Expansion
项目类型:
Runway
项目性质:
Public
项目经费 (USD Millions):
1000
规模:
3.2
规模单位:
km
参加单位:
Federal Aviation Administration[Sponsor]{United States},Chicago Department of Aviation[Operator]{United States},Walsh Construction[Construction]{United States},Federal Aviation Administration[Sponsor]{United States},Chicago Department of Aviation[Operator]{United States}
项目状态:
Completed
开始时间:
2016
结束时间:
2020
项目说明:
November 2020 - Project completed; June 2019 - Federal Aviation Administration to provide USD65mn for airport which will be partially used for Runway 9C/27C; August 2016 - Ground breaking ceremony held; Project is part of USD6bn O'Hare International Airport Modernization Programme; 9C/27C Runway is 2 miles long and 200 feet wide; Project will be the airport's sixth parallel runway