August 2021 - Construction underway; January 2020 - Construction commenced; December 2019 - Angers Loire Metropolitan chose Alstom for 20 trains for tram line; June 2018 - Colas has won 2 contracts worth total of EUR63mn (USD73.55mn) for the construction of the tram line; March 2017 - Maine-et-Loire department approved the construction of tram line; Works of the tramway began in January 2020; Line will have 19 stations and run along Avenue Patton into the city centre, where it will briefly share tracks with Line A before turning east along Avenue Montaigne, from here it will turn north onto Boulevard de Deux Croix and Boulevard Alloneau to reach the eastern terminus at Monplaisir