国家和地区: |
India |
项目名称: |
Bairabi - Sairang Broad Gauge Rail Link, Mizoram |
领域: |
Mainline |
项目类型: |
- |
项目性质: |
Public |
项目经费 (USD Millions): |
864 |
规模: |
51.38 |
规模单位: |
km |
参加单位: |
SEW Infrastructure[Construction]{India},Vensar Construction Company[Construction]{India},Hindustan Construction Company (HCC)[Construction]{India},Indian Railways[Sponsor]{India} |
项目状态: |
Under construction |
开始时间: |
2015 |
结束时间: |
2024 |
项目说明: |
December 2021 - Construction underway expected completion in March 2024; February 2021 - Line to be completed by 2023; November 2020 - HCC and VCCL has been awarded worth INR2.36bn (USD31.8mn) for construction of Single Line BG Tunnels Lot 14A and Lot 15A; February 2020 - Construction underway, additional fund of INR2.90bn (USD40mn) is required to prevent delay in project; Line will have 32 tunnels of 12.6 km, 142 bridges including 102m high pier bridge and 10 ROBs/RUBs (Road Over Bridge/Road Under Bridge); Project cost - INR65.27bn |
发布时间: |
2015 |