Balharshah (Maharashtra) - Kazipet (Telangana) Third Rail Line
国家和地区: India
项目名称: Balharshah (Maharashtra) - Kazipet (Telangana) Third Rail Line
领域: Mainline
项目类型: Upgrade/Maintenance
项目性质: Public
项目经费 (USD Millions): 357
规模: 201
规模单位: km
参加单位: Government of India[Sponsor]{India},Indian Railways[Sponsor]{India}
项目状态: Under construction
开始时间: 2020
结束时间: 2021
项目说明: August 2021 - Construction underway on Maneru bridge as part of project; April 2021 - Kolnur-Potkapalli section (7.75 km) commissioned; October 2020 - The rail track between Raghavapuram and Kolanur completed as part of the project; February 2020 - INR4.83bn (USD68mn) allocated for the project in FY2021 budget; February 2019 - INR2.65bn (USD37mn) allocated for the project in FY2020 budget; August 2016 - Cabinet Committee on Economic Affairs (CCEA) approved construction of third track on 201km Ballarshah - Kazipet section of Delhi - Chennai line; Project cost - INR24.03bn