Baotou People's Municipal Government[Sponsor]{China},Baotou People's Municipal Government[Sponsor]{China}
项目状态:
Suspended
开始时间:
-
结束时间:
-
项目说明:
July 2021 - Project is suspended; May 2020 - Project suspended in August last year; September 2016 - China's National Development and Reform Commission approved the project; Line will have 22 stations; Project cost - CNY20.19bn