Bordeaux Tramway, Phase-III, Line D (Quinconces - Cantinolle), Nouvelle-Aquitaine
国家和地区: France
项目名称: Bordeaux Tramway, Phase-III, Line D (Quinconces - Cantinolle), Nouvelle-Aquitaine
领域: Light Rail
项目类型: -
项目性质: Public
项目经费 (USD Millions): 307
规模: 9.8
规模单位: km
参加单位: Systra[Consultant/Project Management]{France},Ingerop[Consultant/Project Management]{France},Thales Group[Consultant/Project Management]{France},Transports Bordeaux Metropole[Sponsor]{France},Alstom SA[Equipment]{France}
项目状态: Completed
开始时间: 2018
结束时间: 2020
项目说明: March 2020 - Line D of Bordeaux tramways has therefore been completed in February 2020 with entry into service of Mairie du Bouscat - Cantinolle section, serving 9 additional stations; Project is a part of 33 km Bordeaux Light Rail Phase 3 Extension; Project comprise of 2 sections, Quinconces - Eysines and Eysines - Saint-Medard-en-Jalles; Project Cost - EUR250mn