Delhi Mumbai Industrial Corridor Development Corporation (DMICDC)[Sponsor]{India},Indian Railways[Sponsor]{India}
项目状态:
At planning stage
开始时间:
-
结束时间:
-
项目说明:
July 2021 - Land acquisition works to be expedited; April 2018 - Bids invited for consultancy service for Bhimnath - Dholera section; September 2016 - Report was under scrutiny of Railway Board; Project includes conversion of 29.66 km Botad - Bhimnath rail line to broad gauge and construction of 27.6 km Bhimnath-Dholera new rail line; Project Value - INR4.96bn