Government of Australia[Sponsor]{Australia},Australian Rail Track Corporation (ARTC)[Sponsor]{Australia}
项目状态:
At planning stage
开始时间:
-
结束时间:
2025
项目说明:
February 2022 - Vossloh has secured a EUR90mn (USD102mn) contract to deliver 1.3mn sleepers for the construction of project; November 2021 - Legislative Assembly Committee released its report on the project which will stretch from Melbourne to Brisbane, and made 10 recommendations to tackle some of the issues facing by the project; May 2021 - Project is under reference design and project approvals stage; September 2020 - Community Consultative Committee meeting held in August 2020; March 2020 - Community feedback is being gathered as part of Social Impact Assessment (SIA) process for project; Project includes enhancements and commissioning of dual gauge operations along 49km of the existing Sydney to Brisbane Rail Corridor to enable double stacked trains; Project is part of 1700 km Brisbane - Melbourne Inland Freight Rail Project