国家和地区: |
Hungary |
项目名称: |
Budapest Metro Line 3 Upgrade, Central Hungary |
领域: |
Metro |
项目类型: |
Upgrade/Maintenance |
项目性质: |
Public |
项目经费 (USD Millions): |
886 |
规模: |
17.3 |
规模单位: |
km |
参加单位: |
Swietelsky[Construction]{Austria},BUDAPEST Transport Company-BKV[Sponsor]{Hungary},European Union[Financier]{Belgium},Strabag SE[Construction]{Austria} |
项目状态: |
At planning stage |
开始时间: |
2017 |
结束时间: |
2022 |
项目说明: |
March 2021 - Preparations underway on middle section for reconstruction; November 2020 - Work completed on phase III and work suspended on Phase 2 due to conflicts with the contractor; March 2019 - Phase I opened and work started on Phase III; November 2017 - Renovation began on Phase I; Project is being built in 3 phases, where phase I (North) is between Ujpest-Kozpont and Lehel ter, phase II (middle) is between Lehel ter and Nagyvarad ter and phase III (south) is between Nagyvarad ter and Kobanya-Kispest; Project cost - EUR800mn |
发布时间: |
2017 |