YFC Projects Pvt. Ltd.[Construction]{India},Delhi Metro Rail Corporation[Sponsor]{India}
项目状态:
Under construction
开始时间:
2018
结束时间:
2022
项目说明:
July 2021 - Construction underway and will be completed by March next year; August 2019 - DMRC to procure 24 special coaches that will run as four six coaches trains, 40% of civil work is completed; April 2018 - Centre approved the Detailed Project Report of the proposed extension; Project includes extension of the high speed airport express line from Dwarka sector 21 to Dwarka Sector 25; Project cost - INR3.1bn