国家和地区: | India |
项目名称: | Delhi Metro - Phase III, Pink Line (Mukundpur - Shiv Vihar), Delhi |
领域: | Metro |
项目类型: | - |
项目性质: | Public |
项目经费 (USD Millions): | - |
规模: | 58.59 |
规模单位: | km |
参加单位: | Japan International Cooperation Agency (JICA)[Financier]{Japan},Delhi Metro Rail Corporation[Operator]{India},Hindustan Construction Company (HCC)[Construction]{India},Alstom SA[Construction]{France},China Railway Tunnel Group[Construction]{China},Pratibha Industries[Construction]{India},Continental Engineering Corporation[Construction]{Taiwan},Ircon International[Construction]{India},Hyundai Rotem[Equipment]{South Korea},Bombardier Transportation[Equipment]{Canada},J Kumar Infraprojects Ltd[Construction]{India} |
项目状态: | Completed |
开始时间: | 2011 |
结束时间: | 2020 |
项目说明: | September 2020 - Project is operational; January 2019 - 9.7 km Lajpat Nagar-Mayur Vihar Pocket 1 section opened; October 2018 - Shiv Vihar to Trilokpuri section opened; August 2018 - Moti Bagh - Lajpat Nagar section opened; March 2018 - Majlis Park - South Campus section opened; February 2018 - Trial run began on IP Extn - Maujpur Section; June 2017 - Trial run commenced on 6.5-km Shakurpur-Mayapuri section; Line which is being constructed in Phase III of Delhi Metro Expansion, has been carried out in multiple sections; [B&R] |
发布时间: | 2011 |