Delhi Metro - Phase III, Violet Line Extension, Central Secretariat - Kashmere Gate Section, Delhi
国家和地区: India
项目名称: Delhi Metro - Phase III, Violet Line Extension, Central Secretariat - Kashmere Gate Section, Delhi
领域: Metro
项目类型: -
项目性质: Public
项目经费 (USD Millions): -
规模: 9.37
规模单位: km
参加单位: Shanghai Urban Construction Group[Construction]{China},Delhi Metro Rail Corporation[Operator]{India},Moscow Metrostroy[Construction]{Russia},Era Infra Engineering Ltd.[Construction]{India},Pratibha Industries[Construction]{India},Larsen & Toubro (L&T)[Construction]{India},China Railway First Group[Construction]{China},Hindustan Construction Company (HCC)[Construction]{India},Samsung[Equipment]{South Korea},Japan International Cooperation Agency (JICA)[Financier]{Japan}
项目状态: Completed
开始时间: 2011
结束时间: 2016
项目说明: May 2017 - ITO - Kashmere Gate section opened; August 2016 - Trial run commenced on ITO - Kashmere section; Line was commissioned in 3 sections, 3.2 km Central Secretariat - Mandi House section was completed in June 2014, 0.972 km Mandi House - ITO section completed in June 2015 and last section i.e. 5.27 km ITO - Kashmere section opened in May 2017; Project is part of Phase III of Delhi Metro Expansion; [B&R]
发布时间: 2011
检索历史
应用推荐