State Government of Bayern[Sponsor]{Germany},Porr[Construction]{Austria},European Union[Financier]{Belgium},CDM Smith Inc[Consultant/Project Management]{United States},Deutsche Bahn[Sponsor]{Germany},Flughafen Munchen GmbH[Sponsor]{Germany}
项目状态:
Completed
开始时间:
2018
结束时间:
2021
项目说明:
September 2021 - Project completed; February 2021 - Tunnel to be shelled this summer; September 2018 - Ground breaking ceremony held; March 2018 - Porr has been awarded EUR110m (USD134mn) contract to build the project; Project forms part of Erdinger Ring Closure Railway Line project