Morgan Sindall Group[Construction]{United Kingdom},Story Contracting Limited[Construction]{United Kingdom},ScotRail[Sponsor]{United Kingdom}
项目状态:
Completed
开始时间:
2016
结束时间:
2016
项目说明:
August 2016 - Tunnel reopened after 20 weeks of work; Project covered construction of renewal of 1800m of concrete slab track and installation of more than 4000m of new rails; Project cost - GBP60mn