Hadera East-Lod Railway Line
国家和地区: Israel
项目名称: Hadera East-Lod Railway Line
领域: Mainline
项目类型: -
项目性质: Public
项目经费 (USD Millions): 2401
规模: 64
规模单位: km
参加单位: Israel Railways[Sponsor]{Israel},Netivei Israel[Sponsor]{Israel}
项目状态: Under construction
开始时间: 2020
结束时间: 2026
项目说明: January 2020 - Construction underway on South section while Ministry of Finance has approved only 3 out of 5 stations on North section; October 2019 - Tender launched for section C and D of southern section wile planning underway on northern section; Line will be built in 2 sections, North section which connect Hadera and Kfar Saba and south section which will connect Kfar Saba and Lod; Project cost - ILS8.5bn
发布时间: 2020