Mapna[Construction]{Iran},Isfahan Metro Company[Sponsor]{Iran}
项目状态:
Completed
开始时间:
2001
结束时间:
2017
项目说明:
March 2020 - Project completed in 2017; June 2017 - Phase III (Takhti - Azadi Square) has been completed and testing has begun; November 2016 - Section between Shohada and Takhti of 0.8km has started operations; October 2015 - Phase I (Shohada - Qods) of 11 km has been completed; Project is being carried out in multiple phases