国家和地区: |
Turkey |
项目名称: |
Istanbul Metro Line M7, Kabatas - Esenyurt, Istanbul |
领域: |
Metro |
项目类型: |
- |
项目性质: |
Public |
项目经费 (USD Millions): |
- |
规模: |
43 |
规模单位: |
km |
参加单位: |
Bombardier Transportation[Equipment]{Canada},Istanbul Metropolitan Municipality[Sponsor]{Turkey},Alsim Alarko[Construction]{Turkey},Hyundai Rotem[Equipment]{South Korea},French Development Agency[Financier]{France} |
项目状态: |
Completed |
开始时间: |
2014 |
结束时间: |
2020 |
项目说明: |
November 2020 - Phase III completed in October 2020; February 2020 - Test drive to be launched on May 19, 2020 on phase I and phase II; March 2019 - Testing starts on phase I and phase II; December 2017 - Hyundai-Rotem won contract to supply 120 coaches for project; May 2016 - TBM reached Kazim Karabekir Station; March 2016 - Hyundai rotem has won rolling stock contract; Project is being carried out in 3 phases, 18 km Mecidiyekoy-Mahmutbey and 6.5 km Kabatas-Mecidiyekoy, 18.5 km Esenyurt - Mahmutbey |
发布时间: |
2014 |