国家和地区: |
Indonesia |
项目名称: |
Jakarta MRT System, North - South Line - Phase II, Jakarta (Special City District) |
领域: |
Metro |
项目类型: |
- |
项目性质: |
Public |
项目经费 (USD Millions): |
1569 |
规模: |
12.1 |
规模单位: |
km |
参加单位: |
PT Hutama Karya[Construction]{Indonesia},Government of Indonesia[Sponsor]{Indonesia},Government of Jakarta[Sponsor]{Indonesia},Shimizu Corporation[Construction]{Japan},Japan International Cooperation Agency (JICA)[Financier]{Japan},Sumitomo Mitsui Construction[Construction]{Japan},PT Adhi Karya[Construction]{Indonesia} |
项目状态: |
Under construction |
开始时间: |
2020 |
结束时间: |
2027 |
项目说明: |
August 2021 - Project is under construction; April 2021 - MRT Jakarta has awarded a IDR4.6trn (USD316.8mn) contract to a JV between Sumitomo Mitsui Construction and Hutama Karya for the construction of the phase II; February 2021 - Construction underway, project to be delayed due to the COVID-19 pandemic; February 2020 - MRT signed a contract with the Shimizu-Adhi Karya, a joint venture of Shimizu Corporation and Adhi Karya, to launch the work; October 2018 - JICA signed loan agreements with the Government of Indonesia for loans up to JPY70bn (USD623mn) for phase II; Phase II is divided into two sections - phase 2A (6.3 km) with seven stations and 2B (5.8 km) from Kota station to Ancol with three stations; Phase II will start from Hotel Indonesia Roundabout to Kampung Bandan station in North Jakarta; Project is part of Jakarta MRT System, North - South Line; Project cost - IDR22.5trn |
发布时间: |
2020 |