Jharsuguda (Odisha) - Bilaspur (Chattisgarh) Fourth Railway Line
国家和地区: India
项目名称: Jharsuguda (Odisha) - Bilaspur (Chattisgarh) Fourth Railway Line
领域: Mainline
项目类型: Upgrade/Maintenance
项目性质: Public
项目经费 (USD Millions): 342
规模: 206
规模单位: km
参加单位: Shyam Indus Power Solutions[Construction]{India},ARSS Infrastructure[Construction]{India},Government of India[Sponsor]{India},Indian Railways[Sponsor]{India}
项目状态: At planning stage
开始时间: -
结束时间: -
项目说明: July 2021 - Union Minister for Railways reviewed the project; February 2020 - INR2.8bn (USD39mn) allocated to project FY 2020-21 budget; December 2018 - South East Central Railway puts the project on fast track; September 2016 - ARSS-SIPS JV won contract to Soil investigation, design of bridges, execution of earth work, minor bridges, major bridges and other works; August 2016 - Cabinet Committee on Economic Affairs (CCEA) approved the project; Project cost - INR22.98bn