项目说明: |
September 2021 - Project seek Chinese funds for modern developement while China Eximbank asked Kenya to redo a feasibility study to prove its commercial viability before it extends financing; May 2021 - Project under planning stage; June 2020 - Phase IIB and IIC are stalled due to funding issues; October 2019 - Government of Kenya commissioned Phase IIA; October 2016 - Construction works for Phase IIA launched; May 2017 - Phase I completed; Construction for Phase I started in October 2013; Project to be implemented in 2 phases, Phase I (472 km) Mombasa - Nairobi, Phase II (497 km) Nairobi - Malaba which is further divided into 3 sub-phases, Phase IIA (120 km) Nairobi - Naivasha, Phase IIB (270 km) Naivasha - Kisumu, and Phase IIC (107 km) Kisumu - Malaba; Project is part of transnational rail network between Kenya, Uganda, Rwanda and South Sudan; [B&R] |