Kharagpur (West Bengal) - Adityapur (Jharkhand) Third Railway Line
国家和地区: India
项目名称: Kharagpur (West Bengal) - Adityapur (Jharkhand) Third Railway Line
领域: Mainline
项目类型: Upgrade/Maintenance
项目性质: Public
项目经费 (USD Millions): 202
规模: 132
规模单位: km
参加单位: GPT Group[Construction]{Australia},Government of India[Sponsor]{India},Rail Vikas Nigam Limited (RVNL)[Construction]{India},Indian Railways[Sponsor]{India}
项目状态: Under construction
开始时间: 2017
结束时间: 2021
项目说明: April 2021 - Project will be completed soon; February 2019 - INR2.24bn (USD31mn) has been sanctioned in FY2019-20 budget; March 2018 - 8km Gamharia - Adityapur stretch has been completed; August 2017 - Ground breaking ceremony held; November 2016 - GPT Infraprojects won contract to construct major bridges over Subarnarekha and Kharkai rivers; August 2016 - Cabinet Committee on Economic Affairs (CCEA) approved construction of third track on 132km section between Kharagpur and Adityapur; Project cost - INR13.12bn