Bangladesh Railway[Operator]{Bangladesh},Balaji Railroad Systems Ltd - BARSYL[Consultant/Project Management]{India},Exim Bank of India[Financier]{India},Government of Bangladesh[Sponsor]{Bangladesh}
项目状态:
Under construction
开始时间:
2018
结束时间:
2022
项目说明:
August 2021 - Construction is progressing at extremely slow pace with more then 70% work yet to be completed; September 2020 - Construction progress is slow and project has only registered 18% completion rate as of August 2020; March 2020 - Project is delayed due to a delay in loan processing and approval procedure by the Indian authorities; September 2018 - Construction commenced; August 2015 - Bangladesh Railway signed an agreement with Balaji Railroad System to carry out detailed design and construction supervision; Project cost - BDT6.78bn