国家和地区: | Pakistan |
项目名称: | Lodhran - Raiwind Rail Line Double Tracking Project |
领域: | Mainline |
项目类型: | Upgrade/Maintenance |
项目性质: | Public |
项目经费 (USD Millions): | 377 |
规模: | 370 |
规模单位: | km |
参加单位: | Frontier Works Organisation[Sponsor]{Pakistan},Pakistan Railways (PR)[Sponsor]{Pakistan} |
项目状态: | Completed |
开始时间: | 2003 |
结束时间: | 2015 |
项目说明: | January 2016 - Project inaugurated, installation was completed in November 2015; Project is part of Karachi - Lahore Double Tracking Rail Project which was built in sections, first 15 km of Lodhran - Multan - Khanewal section was completed by May 2005, Lodhran - Khanewal track via Multan was opened for traffic in March 2007 and section between Khanewal and Sahiwal was completed in May 2011; Project cost - PKR40bn |
发布时间: | 2003 |