国家和地区: |
United States |
项目名称: |
MBTA Green Line Extension Project (Lechmere Station - Medford - Somerville) |
领域: |
Light Rail |
项目类型: |
- |
项目性质: |
Public |
项目经费 (USD Millions): |
2300 |
规模: |
7 |
规模单位: |
km |
参加单位: |
HDR Inc[Consultant/Project Management]{United States},HNTB Corporation[Design/Architect]{United States},US Federal Transit Administration (FTA)[Sponsor]{United States},Gilbane Building Company[Consultant/Project Management]{United States},Massachusetts State Government[Sponsor]{United States},Massachusetts Bay Transportation Authority[Sponsor]{United States},Government of United States[Sponsor]{United States},AECOM[Design/Architect]{United States} |
项目状态: |
Under construction |
开始时间: |
2013 |
结束时间: |
2021 |
项目说明: |
December 2021 - Construction underway; October 2017 - GLX Constructors, Green Line Partners, and Walsh Barletta Granite, contract is expected to be awarded in December 2017; Construction commenced in January 2013; MBTA has awarded a contract for program management and construction management to the HDR/Gilbane Team, a joint venture of HDR Engineering, Inc. and Gilbane Building Company |
发布时间: |
2013 |