August 2021 - Khandwa - Akot still incomplete and Akola - Akot completed; October 2020 - Construction underway; February 2020 - Amount of INR3.6bn (USD52mn) has been approved for gauge conversion on Mhow - Sanawad section; February 2019 - INR3.55bn (USD49.8mn) received under the budget for the under construction project; May 2016 - Construction commenced on Khandwa - Sanawad; Project is being carried out in multiple section, where Akola - Khandwa section and Ratlam - Mhow sections are already completed; Project cost - INR14bn