国家和地区: |
Bolivia |
项目名称: |
Montero (Santa Cruz) - Bulo Bulo (Cochabamba) Rail Line |
领域: |
Mainline |
项目类型: |
- |
项目性质: |
Public |
项目经费 (USD Millions): |
- |
规模: |
148.7 |
规模单位: |
km |
参加单位: |
China CAMC Engineering[Construction]{China},Government of Bolivia[Sponsor]{Bolivia},China Railway Construction Corporation (CRCC)[Construction]{China},Construcciones Viales e Hidraulicas SA (Convisa)[Construction]{Bolivia} |
项目状态: |
Under construction |
开始时间: |
2013 |
结束时间: |
2020 |
项目说明: |
June 2021 - Construction underway; December 2020 - Works restarted on the project with 88% work completed; October 2019 - Section II completed; June 2018 - Section III completed was completed in early 2016; December 2015 - Contract terminated with China CAMC Engineering, that was appointed for section I; Project is divided in 3 sections; Project cost - USD250mn; [B&R] |
发布时间: |
2013 |