A.S. Associated Engineering[Construction]{Thailand},State Railway of Thailand (SRT)[Operator]{Thailand},Sino-Thai Engineering and Construction[Construction]{Thailand}
项目状态:
Under construction
开始时间:
2020
结束时间:
2021
项目说明:
August 2021 - Construction underway; April 2020 - Both the sections are under construction; August 2017 - AS associated engineering and Sino Thai Engineering and Construction PLC won contract for construction of section 1 and 2 respectively; Project is being built in two sections with section 1 from Nakhon Pathom to Nong Pla Lai (93 km) and section 2 from Nong Pla Lai to Hua Hin (76 km); Project cost - TBH15.72bn