项目说明: |
September 2021 - Pre-construction phase expected to conclude in 2022; June 2021 - In FY2021, Metro plans to advance pre-construction design packages for site preparation, demolition, and the new HRO facility; February 2021 - Washington Metropolitan Area Transit Authority has selected Hensel Phelps Construction and Stantec to design and deliver project; August 2019 - WMATA is seeking the services of Design Builder to complete the design, construction, testing, and commissioning; Project will serve Metrorail vehicles and car track equipment maintenance for 40 rail cars, a rail car truck shop, and storage tracks for up to 24 rail cars and companies will provide the design, construction, testing and commissioning for the project, which includes construction of a new rail connection from the project site to the Metrorail Orange Line |