Trakcja System[Construction]{Poland},Porr[Construction]{Austria},European Union[Financier]{Belgium},PKP Polskie Linie Kolejowe[Sponsor]{Poland}
项目状态:
Under construction
开始时间:
2020
结束时间:
2023
项目说明:
November 2021 - Reconstruction of tracks and railway traffic control devices is underway; March 2020 - PKP Polskie Linie Kolejowe SA is preparing design documentation; September 2019 - Contract worth EUR282mn (USD310mn) awarded to Porr; Total of 135 km of track and 148 sets of switches will be replaced on the 71 km long stretch between Kalina and Rusiec Lodzki, while the complete control and safety system will be modernised along with the catenary and 17 level crossings