国家和地区: | Italy |
项目名称: | Rome Metro Line C, Lazio |
领域: | Metro |
项目类型: | - |
项目性质: | Public |
项目经费 (USD Millions): | 4130 |
规模: | 25.6 |
规模单位: | km |
参加单位: | Hitachi Rail STS[Equipment]{Italy},Cooperativa Muratori e Braccianti di Carpi[Construction]{Italy},Vianini[Construction]{Italy},Astaldi[Construction]{Italy},Ansaldo STS[Equipment]{Italy},Ansaldo Breda S.p.a[Equipment]{Italy},Government of Lazio Region[Sponsor]{Italy},Consorzio Cooperative Costruzioni CCC Societa Cooperativa[Construction]{Italy} |
项目状态: | Under construction |
开始时间: | 2007 |
结束时间: | - |
项目说明: | February 2022 - Work is not yet finished; December 2020 - The amendment for financing has been rejected to complete C of Rome metro; February 2019 - Amba Aradam and Colosseum-Roman Forum stations to open in 2023; June 2015 - 5.4 km section between Parco di Centocelle - Lodi opened; November 2014 - 12.5 km section between Monte Compatri-Pantano and Parco di Centocelle opened; Project cost - EUR3.739bn |
发布时间: | 2007 |