Rail Vikas Nigam Limited (RVNL)[Sponsor]{India},ARSS Infrastructure[Construction]{India},Asian Development Bank (ADB)[Financier]{Philippines},Voyants Solutions Pvt Ltd[Consultant/Project Management]{India}
项目状态:
Under construction
开始时间:
2014
结束时间:
2021
项目说明:
February 2021 - Construction scheduled for completion by December 2021; November 2020 - RVNL awarded consultancy contract for Bargarh Road to Barpali & Badmal to Titlagarh section; February 2020 - The Union Budget 2020-21 has allocated INR3.82bn (USD53mn) for the project, ARSS Infrastructure receives work order from Rail Vikas Nigam; January 2019 - 14.2 km of Barpali-Dungaripali and 17.354 km Balangir-Deogaon section completed; Work began in 2014; Project Value - INR13.51bn