African Development Bank (AfDB)[Financier]{Cote d`Ivoire},ONCF[Sponsor]{Morocco}
项目状态:
Under construction
开始时间:
2016
结束时间:
-
项目说明:
September 2018 - Construction underway; August 2017 - Construction commenced on section of Casablanca-Marrakesh railway line; January 2016 - AfDB lends USD112.3mn for the project; Project includes track-doubling on the 142km line from Settat to Sidi Ghanem near Marrakech; Project is being carried out in sections, with Skhour - Benguerir and Sidi Ghanem - Marrakesh sections of the line