February 2021 - Construction underway while works on Zapresic - Savski Marof section completed; August 2020 - Construction underway while works commenced in May 2020; February 2020 - Swietelski won contract for reconstruction of railway section; April 2014 - HZ Infrastruktura applied for a loan from EBRD to help finance the project; Project is part of Croatia's programme to invest EUR1.5bn (USD1.6bn) in railway infrastructure upgrades; Project cost - HRK366mn