国家和地区: |
Brazil |
项目名称: |
Transnordestina Railway Revitalisation Project, Salgueiro - Porto de Suape Section, Pernambuco |
领域: |
Freight |
项目类型: |
Upgrade/Maintenance |
项目性质: |
Public |
项目经费 (USD Millions): |
- |
规模: |
544 |
规模单位: |
km |
参加单位: |
Superintendencia do Desenvolvimento do Nordeste[Sponsor]{Brazil},Brazilian Development Bank (BNDES)[Financier]{Brazil},Companhia Siderurgica Nacional (CSN)[Sponsor]{Brazil},Banco do Nordeste[Financier]{Brazil},Valec[Sponsor]{Brazil},Odebrecht[Construction]{Brazil} |
项目状态: |
Under construction |
开始时间: |
2006 |
结束时间: |
- |
项目说明: |
August 2021 - Construction underway; December 2020 - Construction resumed in July 2020; June 2020 - Government is considering resumption of Transnordetina railway project in 2020, which has been paralyzed since 2017; July 2018 - Construction work 41% completed; Project is part of 1753 km Transnordestina Railway Revitalization, BRL13.2bn (USD2.48bn) Project; Project Value - BRL4.7bn (USD1.51bn) |
发布时间: |
2006 |