Tyne And Wear Metro Upgrade, Pelaw - Bede Track Doubling Project, North East
国家和地区: United Kingdom
项目名称: Tyne And Wear Metro Upgrade, Pelaw - Bede Track Doubling Project, North East
领域: Metro
项目类型: Upgrade/Maintenance
项目性质: Public
项目经费 (USD Millions): 140
规模: 2.8
规模单位: km
参加单位: Nexus[Sponsor]{United Kingdom},Government of United Kingdom[Sponsor]{United Kingdom},Buckingham Group[Construction]{United Kingdom}
项目状态: Under construction
开始时间: 2022
结束时间: 2022
项目说明: January 2022 - Construction commenced; October 2021 - Work to dual the track is expected to start in September 2022; May 2021 - Buckingham Group Contracting has won a GBP55mn (USD78mn) contract to carry out track doubling works on the Tyne and Wear Metro; July 2020 - Procurement process to expand capacity on the Tyne & Wear Metro has begun; March 2020 - GBP100mn (USD127mn) funding scheme was agreed by the UK government for the project; Doubling will be carried out on the 800m Pelaw-Hebburn section, the 1.4km Hebburn-Jarrow section and the 600m Jarrow-Bede section; Project cost - GBP103mn
发布时间: 2022