国家和地区: | India |
项目名称: | Virar - Dahanu Rail Line Quadrupling Project (MUTP-III), Maharashtra |
领域: | Commuter Rail |
项目类型: | Upgrade/Maintenance |
项目性质: | Public |
项目经费 (USD Millions): | 478 |
规模: | 63 |
规模单位: | km |
参加单位: | Mumbai Rail Vikas Corporation (MRVC)[Sponsor]{India},Ministry of Railways - India[Sponsor]{India},World Bank[Financier]{United States},Asian Infrastructure Investment Bank[Financier]{China},Rail India Technical & Economic Services (RITES)[Consultant/Project Management]{India},Maharashtra State Government[Sponsor]{India} |
项目状态: | At planning stage |
开始时间: | - |
结束时间: | 2024 |
项目说明: | February 2021 - CIDCO approves land transfer for the project; October 2020 - Project has been delayed by two years due to land acquisition issues; February 2020 - Project received funding as part of MUTP 3; November 2019 - AIIB has agreed to provide USD500mn for MUTP-III; Project includes construction of third and fourth lines between Virar and Dahanu; Project is being planned under INR109.47bn (USD1.52bn) Mumbai Urban Transport Project Phase-III (MUTP III); Project cost - INR35.78bn; [B&R] |