Anchorage Port, New Petroleum and Cement Terminal Project (Phase - I), Alaska
国家和地区:
United States
项目名称:
Anchorage Port, New Petroleum and Cement Terminal Project (Phase - I), Alaska
领域:
Port Expansion
项目类型:
Dry Bulk,Liquid Bulk
项目性质:
Public
项目经费 (USD Millions):
200
规模:
-
规模单位:
-
参加单位:
Pacific Pile & Marine LP[Construction]{United States},US Department of Transportation (DoT)[Sponsor]{United States}
项目状态:
Under construction
开始时间:
2020
结束时间:
2021
项目说明:
August 2021 - Construction underway; May 2020 - Construction started in late April and is expected to be completed by late 2021; November 2019 - US DOT has approved USD25mn grant funding for the project; July 2019 - Anchorage Assembly allowed city officials to award a USD42.1mn contract to Pacific Pile and Marine to build the new petroleum and cement terminal; New terminal will support the transmission of refined petroleum and cement from bulk shipping carriers to onshore pipelines and storage facilities at the Port of Alaska