April 2021 - Construction underway; January 2021 - USD1.5bn will be invested in three port projects this year including Chancay megaport; June 2018 - Cosco Shipping to invest USD500mn in construction of Chancay port; February 2017 - Port expected to start commercial operations in January 2020; May 2016 - Construction commenced; Project is part of USD1.85bn Chancay port complex, this phase include solid, liquid and rolling cargo bulk terminal and a Port Operating Area, an Entrance Complex and a 1.8 km long three-lane Deep Tunnel; Project cost - USD460mn